How this Report is Generated

  1. Categorize as Backlog all tasks that are:
    1. in project Kanban
    2. and in a column whose title includes the text Backlog
  2. Categorize as In Progress all tasks that are:
    1. in project Kanban
    2. and in a column whose title includes the text In-progress
    3. and not in any rules above
  3. Categorize as Blocked all tasks that are:
    1. in project Kanban
    2. and in a column whose title includes the text Blocked (externally)
    3. and not in any rules above
  4. Categorize as Done Column all tasks that are:
    1. in project Kanban
    2. and in a column whose title includes the text Done (within RelEng)
    3. and not in any rules above
  5. Categorize as Other all tasks that are:
    1. in project Kanban
    2. and not in any rules above
  6. Delete any remaining tasks